The third runway in Sheremetyevo will cost 17.6 billion rubles.


Moscow. December 24. The cost of the contract for the construction of the third runway at Sheremetyevo is 17,588 billion roubles, is spoken in materials of the website of public procurement.

Appropriate purchase from a single supplier – OOO “Transstroymekhanisatsiya” – posted FSUE “Administration of civil airports (airfields)”.

It is indicated that the completion date is set for December 2019, it was assumed that the runway will be built by 2018.

In 2015 it is planned to allocate 4,652 billion rubles, in 2016 – 866 million rubles, in 2017 – 2,234 bn in 2018 -4,761 bn in 2019 – 5,075 billion rubles.

The tender for construction of R-3 was announced in September 2011. Start of construction of the strip – 2012. In December 2011 JSC “Engineering Corporation “Transstroy (Inzhtransstroy”) was recognized as a winner in the contest. The cost of the contract is $ 22,418 billion. However, in may 2015, the company halted construction, but in her case was a supervision procedure was commenced. Later “Inzhtransstroy” has addressed in court with the claim about cancellation of the contract for construction.

In October, the government approved a “Transstroymekhanisatsiya” (part of the Mostotrest group) new artist of the project on construction of the runway of the airport “Sheremetyevo”. The General Director “the Sheremetyevo” Michael Vasilenko has repeatedly said that the runway will be built in the period to 2018.