The new building of the Investigative Committee will cost 5.5 billion rubles.


Design and construction of a new building of the Investigative Committee in Moscow will cost 5.6 billion rubles, follows from the draft of a government order published on an official portal of projects of normative legal acts. Compared to the estimate approved by decrees of the Prime Minister, Dmitry Medvedev, in 2012 and 2014, construction fell by 273 million rubles.

In the original draft it was stated that the building should be commissioned in 2018. In the published draft of the resolution States that the building will be completed no earlier than 2019.

The construction of the new building of the TFR in the Technical lane began in August of 2015. According to the official report on the website of the Committee of state construction supervision of Moscow, the new complex will be a “design variable height” (2-11-14-18 floors and three underground levels with a total area of 59.5 thousand sq. m.

The architectural appearance of the new SKR drew of JSC “Moscow architectural art design Institute (MAGPI) named after Academician Polanski”. According to the portfolio project, the walls will be lined with natural granite, and the building will be connected by a passage with the old structure. Inside provided rooms, cultural center, sports complex. On the first floor of the building will be “double-height lobby,” playing the role of the foyer for the hall for the 738 seats, with a projection room and other functional areas. In addition, the first floor meeting room and pool. On the second floor is the dining room with a VIP room and a bar.

On the underground levels — Parking with car wash and inspection area machines, a shooting gallery and a “protective structure of civil defense”. Top, 18 th floor is “block Chairman SKR. For the Chairman of the TFR Alexander Bastrykin has also a separate entrance from the service Elevator. Above him on the roof of the building will be equipped with a helipad.

The designer of the new building is organized by OAO “Moskapstroy”, follows from the documents published on the official portal of public procurement. Moskapstroy” — formerly the largest contractor for the construction of the Moscow authorities. In 2013, the company passed under control AFK “System” Vladimir Yevtushenkov.

The General contractor of the construction is LLC “Kaskad-Energo”, follows from the information booth on the website of the TFR. The company website States that it is part of a group of “Tashir” Samvel Karapetyan.

Other tenders related to the construction of the building of the TFR, from August 2015 have not been published on the public procurement portal.