SIMFEROPOL, 11 December. The supply of electricity on the energy bridge from the Krasnodar region in the Crimea will be suspended on the night of December 12th at 8 hours due to maintenance work, reported in government of Crimea.
See also
In the capital of Crimea included street lighting after two weeks of a blackout
“For repairs of transmission lines, approximately from 23 hours to 11 December 2015 to 7 am on 12 December 2015 will be disconnected OL 220 kV Kamysh-Burun – Taman”, – stated in the message.
Due to restrictions in settlements will be reduced the limits of power consumption. Disconnection of consumers will be based on priorities provide electricity to socially significant facilities, according to the government of the Crimea.
In particular, limitations in the supply of electricity will be introduced in Belogorsk and Krasnogvardejskiy districts of the Republic of Crimea. Each locality area will alternately remain without electricity 2-3 hours a day. In Simferopol, it was decided that the trolleybuses on 12 December will go out on the line three hours later at 8 am.
For the last day on the power lines in Crimea, which is three weeks living in an emergency mode (emergency), occurred 55 accidents. According to heads of municipalities, the accident at the power grids in the Crimea, occur almost daily, often suffer from residents of Yalta. Experts attribute this to the deterioration of electric grid. “When I was driving from Moscow, I was told that in the Crimea the 90’s. Guys, you have a beautiful 70”, – said earlier the Minister of fuel and energy of the Republic Svetlana Borodulina.
Now in the Crimea are specialists of Rostechnadzor, checking all the mains, including illegal connections.
Termination of electricity supply
On November 22 due to the accident at the power lines in the Kherson region were fully discontinued the supply of electricity from Ukraine in Crimea.
See also
Medvedev called “genocide and disgusting” energy blockade of the Crimea Ukraine
In the Republic introduced a state of emergency associated with the deficit. To save on the Peninsula began to use rolling blackouts of consumers. Now one of four high-voltage lines coming from Ukraine, it gives the Peninsula about 150 MW.
The first line of the power bridge from the Krasnodar region in Kuban started on 2 December. In the last few days on the Peninsula with her help was delivered about 285 MW of electricity. A second line is planned to run until 15 December, it will give more than 200 MW.